Cycle Time
Cycle time is the time required to process one piece
For example,
Grinding Cycle time = 100 sec
It includes,
Loading Cycle time + Auto Cycle time + Unloading time
=20 sec +75 sec +5 sec
=100 sec
ie Every 100 sec , we can get one component
Cycle time is the time required to process one piece
For example,
Grinding Cycle time = 100 sec
It includes,
Loading Cycle time + Auto Cycle time + Unloading time
=20 sec +75 sec +5 sec
=100 sec
ie Every 100 sec , we can get one component
Throughput Time
Throughput time = Sum of ( Cycle time in entire process of a component)
Total processing time for one component
For example,
Bearing ring throughput time = 240 sec
It means
Parting cycle time +Grinding cycle time +Turning cycle time
=60 sec +100 sec+80 sec
=240 sec
ie To process one bearing ring, the total time required is 240 sec
Lead time
Lead Time = Sum of ( Cycle time in the entire process of a component) + all non-value added times in the system
ie Lead time = Throughput time + all waste/delay time in the system
For example,
Bearing Lead time = 2 days,
It means = 240 sec+all delays leads to 2 days
No comments:
Post a Comment